Loving the Process

Regular customers will know that we’re putting a third floor onto our building.  At least, we’re trying to. Turns out the construction process is a steeplechase lined with hidden delays.  Like, for instance, the giant wire that crosses through our construction zone.

Hydro took three weeks to inform us that the line belongs to Bell.  Bell took six weeks to inform us that the line actually belongs to Rogers.  Rogers took only thirty minutes to get a technician here (!)… to inform us that the problem will be referred to another department that may or may not get back to us within three weeks.

Sigh.  Did I say steeplechase?   I meant freeze tag.

 